KINGS WAY PROGRAM 5 - November 2
• Rough-in of structured wiring, security, central vacuum and rough plumbing • Rough electrical work & HVAC System KINGS WAY PROGRAM 6 - November 9 • Install fireplace • Insulation process KINGS WAY PROGRAM 7 - November 16 • Discuss exterior work being completed on home • Learn about granite countertop surfaces KINGS WAY PROGRAM 8 - November 23 • Install cultured stone & brick KINGS WAY PROGRAM 9 - December 7 • Hang & mud drywall KINGS WAY PROGRAM 10 - January 4, 2009 • Installation of hrdwood floors • Finish carpentry work • Lay ceramic tile KINGS WAY PROGRAM 11 - January 11, 2009 • Finish plumbing, electric, structured wiring & central vacuum system • Install countertops • Install closet storage systems KINGS WAY PROGRAM 12 - January 18, 2009 • Install carpeting • Discuss landscaping process • Tour finished "Sanctuary of Delafield" single family condominium home ![]() |
||||||